Govt. of Sindh provided 18 acres of land and Funds for the construction
of the main building. PABC provides funds for the execution and
operation of the project. Project was started in 1993 and was planned to
be completed in 3 phases -
Phase I : Main Hospital Building, OPDs, Installation of
Nuclear Medicine
& Radiotherapy Equipment, Day Care Chemotherapy, Nurses
Hostel
----------- Completed in 1997 --------
Phase II: 200 Bed Wards, Auditorium, Library, Installation
of Additional
Equipment
----------- Completed in 2007 --------
Phase III: Research Laboratories, PET & Bone Marrow
Transplantation
Facilities, Residential Colony
---------- Later ---------
-
Essential
equipment purchased and installed by mid 1999
-
KIRAN
started functioning partially in December 1999
-
Formal
Inauguration by Governor Sindh in September 2001
-
Phase
II started in 2008.
|