Karachi Nuclear Power Plant (KANUPP)


Safety Upgrades

While maintaining its original safety and public risk targets, KANUPP is incorporating all possible safety improvements and upgrades to meet the current international safety standards.

 

In-Service Inspection of Equipment in Progress
In-Service inspection of equipment in progress

Major areas of improvement being undertaken to ensure continued safe operation are:

 

Obsolescence

  • Replacement of Computer, Control and Instrumentation System.

  • Replacement of Fire Alarm System.

  • Replacement of Nuclear Power Instrumentation System.

  • Replacement of Fuel Handling Control Computers.

Design Safety

  • Updating KANUPP Final Safety Analysis Report (KFSAR).

  • Performing PSA Level-1

  • Improving Loss of Coolant Accident (LOCA) Handling Capabilities.

  • Improving Emergency Core Cooling Reliability.

  • Initiating Environmental Qualification Programme.

  • Improving Secondary Heat Sink Reliability

  • Improving Reliability of Emergency Power

  • Improving Control Room Habitability

  • Reviewing Seismic and other Hazards.

Operational Safety

  • Initiation of In-Service Inspection (ISI) Programme.

  • Improving Maintenance Standards

  • Improving Conduct of Operations.

  • Modernizing Operating Policies and Principles (OP&P).

  • Improving Emergency Operating Procedures (EOP).

  • Establishment of QA Programme.

  • Improving Manpower Development.

  • International Computer Networking.

Ageing

  • Assessment of Reactor Fuel Channels (RFC) Integrity.

  • Improvement in Carbon Dioxide (C02) System.

  • Fuelling Machine Ageing.

  • Refurbishment of valves in the Emergency Injection System.

  • Refurbishment of Protective System Dump Valves.

Digital control/instrumentation panels
Testing of new digital control and instrumentation panels













 