Chashma Nuclear Power Plant-1 (CHASNUPP-1)
A Source of Economical and Environment Friendly Energy


Plant Performance

CHASNUPP-1 has completed 3 cycles of its operation. Its performance has improved over the time which is quite evident from the following performance indicators.

Indicator

Operating period till RFO-1

Operating period between RFO-1 & 2

Operating period between RFO-2 & 3

No. of outages

28

16 

08 

Availability factor (%)

70.2 

84.8

96.38

Net Capacity factor (%)

64.2 

 76.8

92.94 

















 