Milestones & Key Dates
|
Key Date |
Milestone |
|
31
Dec. 1991 |
Signing
of Contract |
|
25
Feb, 1992 |
Contract
Validation |
|
26
Dec. 1992 |
Ground
Breaking |
|
03
July, 1993 |
Construction
Permit |
|
18
Nov., 1993 |
First
Concrete Pour
|
|
03
July, 1999 |
Fuel
Loading Permit
|
|
22
Nov., 1999 |
First
Fuel Loading
|
|
03
May, 2000 |
First
Criticality
|
|
13
Jun, 2000 |
Connection
to Grid |
|
15
Sep., 2000 |
Commercial
Operation |
|
25
Sept., 2000 |
Provisional
Acceptance |
|
29
Mar., 2001 |
Formal
Inauguration |
|
05
May, 2004 |
Final
Acceptance |
|


  









 |
|